What "From Drawing / Scheduled / Counted / Derived / Estimated" Mean on a BOM

3 min read

When a takeoff lands on your desk, the pressing question isn't "what's the total" — it's "which numbers can I use as-is, and which do I need to look at myself?"

Two numbers in the same spreadsheet can be worlds apart in reliability. A section read straight off a schedule and a section the estimator assumed look identical in a cell — but one is almost never wrong and the other can be a full size off.

So every row carries two bases.

Two axes, kept separate

Section basis — how the section was determined:

ValueMeaning
From drawingStated on a schedule or the drawing face
EstimatedNot stated; assumed from span, load or similar members

Quantity basis — how the count was determined:

ValueMeaningTypical error
ScheduledCount given in a schedule~0
CountedCounted off the plan1–3%
DerivedFrom spacing and bay count5–15%
EstimatedNo basis on the drawings15%+

These are independent. A very common case: the section is from the drawing (the schedule gives C180×70×20×2.5) but the count is derived (the drawing only gives @1200 spacing). Trust the section; check the count.

Why not collapse this into one confidence score

A single percentage reads cleaner but can't be acted on. A reviewer needs to know what to go look at:

  • Section in doubt → check the schedule, check the details
  • Count in doubt → check the plan, count it again

Collapse them and that's gone. You're left with "85% confident" and no idea which sheet to open.

How to review

  1. Look at the review tonnage as a share of total. Normally 2–8%. Above 15% means

the drawings themselves are incomplete, or too much was assumed.

  1. Only review the derived and estimated rows. From-drawing and scheduled rows carry

most of the tonnage but almost never move.

  1. Sort by weight. A 49-tonne derived row is worth twenty minutes. A 0.3-tonne one

is worth a glance.

  1. Cross-check. Column counts reconcile against anchor bolts; bay counts against the

grid. Two sources agreeing promotes "counted" to effectively reliable.

A real example

A plant project: 2011.5 tonnes across 142 rows.

Basis pairTonnesShare
From drawing + Scheduled1967.397.8%
From drawing + Derived27.21.4%
Estimated + Counted17.00.8%

44.2 tonnes to review — 2.2%. The reviewer opens 3 rows, not 142.

Why this is worth being strict about

Takeoff numbers become purchase orders and bids. A 5% error on a multi-million contract is real money — and you don't know which row it's in unless every row states where it came from.

Stating it is cheap. Not stating it is expensive.